Guest guest Posted June 4, 2005 Report Share Posted June 4, 2005 Mold attacks floor tiles at town's schools By JEFF MILL, Middletown Press StaffPORTLAND -- Large sect06/04/2005 Email to a friend Voice your opinion Printer-friendly http://www.middletownpress.com/site/news.cfm? newsid=14640363 & BRD=1645 & PAG=461 & dept_id=10856 & rfi=6 ions of the flooring in the high school/middle school complex will have to be pulled up and replaced after tests revealed microbial growth in the glue that holds the tile in place. Officials are still working to develop a hard number for the repair project; but they said Friday the work will almost certainly cost " in the low six figures. " At present, an environmental specialist said, the growth is contained in the glue (or mastic) beneath the floor tiles, and does not represent a hazard to students or faculty or staff. Tests have disclosed 19 individual areas in the two schools where the growth has been discovered, the specialist, M. Weekes, said. Weekes, who is president of Abacus Environmental Inc., of Ellington, said, " It is highly unlikely the growth will become airborne. " " Right now, we know to some extent that it's contained, " said a lawyer who is representing the town in ongoing discussions with the company that installed the tile. Weekes described the growth as a common mold that was created in one of two ways: in some cases, the growth developed when the tile was laid on damp concrete. But in other cases, he said, the poorly aligned or misaligned floor tiles allowed cleaning water to seep into the glue and begin the microbial growth. The growth is an extension of the what town officials contend is the poorly installed flooring in the new $39 million school. Concerns about the flooring have bedeviled school officials and delayed completion of the project. The Board of Selectmen met in a special emergency session Friday evening to hear an explanation of the scale of the problem, and to begin to set in motion the process of bringing the issue before residents at a town meeting later this month or in early in July. Lawrence G. Rosenthal, the attorney working on the tile issue for the town, told the selectmen he expects much of the cost of replacing the tiles can be regrouped through lawsuits against the company that installed the flooring. But, Rosenthal added, the remedial work must be undertaken immediately. " The town cannot wait, " he insisted. " The problem is not going to go away. " Weekes said the flooring will have to be torn up in the affected areas and the glue taken up, then the under floor cleaned with an anti-bacterial solution before a new floor is laid. " The problem, " Rosenthal interjected, " is the short time frame. " He said the work must be done this summer to eliminate any chance of the growth intensifying or spreading. " We don't want this lying around until next fall, " when the students come back into the building. " It's not airborne, and it's not growing up the wall, " Rosenthal said. " But, if you don't fix it, you're going to have that problem. " Donna W. Finkelstein, the chairwoman of the School Building Committee, said in the meantime, Bengston the director of building and grounds maintenance for the school department, has begun applying " an anti-microbial solution " to the floor during every cleaning in an effort to retard any further growth of the mold. Weekes said the growth has been found mainly in three areas: in the music and art section of the middle school adjacent to the new auditorium; in a lower-level hallway in the middle school; and in the lower level of the science wing of the high school. Finkelstein said the affected flooring would have to be removed under more or less the same conditions that are used to remove asbestos, to keep the mold spores from spreading throughout the building First Selectwoman S. Bransfield said she expects the building committee to come before the selectmen next week with a firm cost estimate. She said she hopes to put the issue before residents at a town meeting on June 20. The earliest the town could award a contract could be July 7. " You need to be prepared to have some sections of the building not available when the building reopens " in September, Weekes cautioned. Selectmen W. Flood said he was prepared to go to " double shifts " if need be to correct the problem before school reopens. Weekes added, however, that " another problem is most of the contractors who do this kind of work are already tied up for the summer. " In addition to the selectmen, Interim Superintendent of Schools Dean T. Toepfer attended the meeting, as did Board of Education members Honore Kenney and Allan . At the conclusion of the meeting, Selectman H. observed, " We've got to spend the money; its a `no-brainer.' " " We have no choice, " his colleague, selectman W. Kutz agreed. Ironically, it was what school building committee members have characterized as " sloppy work " that led to the discovery of the mold in the first place, Weekes said. " We probably never could have discovered this if the floor tile has been put down correctly, " he said. To contact Jeff Mill, call (860) 347-3331 ext. 221 or e-mail jmill@.... ©The Middletown Press 2005 Email to a friend Voice your opinion Printer-friendly Top Quote Link to comment Share on other sites More sharing options...
Recommended Posts
Join the conversation
You are posting as a guest. If you have an account, sign in now to post with your account.
Note: Your post will require moderator approval before it will be visible.